Project Details

This project consisted of improving a fire and police training facility for the city of Murfreesboro. The Owner had an accelerated schedule due to a national event they had to host on site.

Prior to obtaining the permit at the pre-construction meeting, we mobilized machines so we could start as soon as we had the permit in hand. We had multiple crews working on different activities for the duration of the project to meet the tight schedule. We streamlined our self-performed work and subcontracted work to finish the project two weeks early.

 

Type of Project

Site Development

Scoped Performance

Demolition, 46,000 CY excavation, rock excavation, drainage, wet utilities, electrical, 100,000 SF concrete pavement, landscaping, asphalt pavement, and roadway improvements

Duration

90 Days